Re: [Emerald] Calls Consolidation Process

Dale E. Reed Jr. ( (no email) )
Thu, 01 Apr 1999 20:36:52 -0800

"Robert H. Clugston" wrote:
>
> I didn't understand what you meant about the key constraints on the
> Callhistory table?

The original Emerald DB Schema only allowed one summary record
per month. With Emerald 2.5, we can now do atleast 3 (Normal, Primary,
and Toll). Therefore, you have to remove the primary key. You can
do this by double clicking on the table, selecting the advanced
options, and removing the primary key.

-- 

Dale E. Reed Jr. Emerald and RadiusNT__________________________________________IEA Software, Inc. www.iea-software.com